Ongoing Incident

Major incident Brown Muir Mast Salterhill Relay East Mains Relay Miltonhill Relay Kellas Relay Sunnyside Relay Cul Mor Relay Ark Childcare Relay Newton Relay Glen of Rothes Relay Lochnabo Conasg Relay
2025-06-15 21:35 BST · 2 days, 12 hours, 53 minutes

Updates

Resolved

Resolved

June 18, 2025 · 10:28 BST
Investigating

An engineer is back on-site this morning to refuel the generator and resolve some issues that have appeared overnight. Current estimate from SSEN for restoration of power is 1pm today.

https://powertrack.ssen.co.uk/powertrack#RA9721

June 16, 2025 · 10:06 BST
Issue

We have confirmed that an SSE power outage is affecting our Brown Muir mast which has knocked out some equipment. An engineer is on route to the site with a generator to ensure that the site remains powered overnight and to restart the offline equipment.

June 15, 2025 · 22:12 BST
Issue

We are investiaging an issue at our brownmuir mast site.

June 15, 2025 · 21:35 BST

← Back